PT. KALIMANTAN ENERGI UTAMA
|
Location |
: |
Sungai Danau, Kota Baru, South Kalimantan |
|
Client |
: |
PT. Kalimantan Energi Utama |
|
Type of Contract |
: |
OB Removal, Coal Getting & Coal Hauling
to CCP |
|
Contract Period |
: |
August 2002 - August 2007 |
Project location at PT. Kalimantan Energi Utama ( owner
concession ), Sungai Danau, Kotabaru, South Kalimantan
Contract validity up to August 2007. Production target is
30.000 MT coal per month with average striping ratio 5.
Madhani's scop of works are exacavate overburden, haul, dump
and spread at waste dump area, and exctraction and hauling ROM
coal and road maintenance for 20 km distance to CCP ( Coal
Processing Plant )
|
 |